| Dr. Reardon's hanger is making slow but steady progress. This
is a 50' x 60' 'pole' type building. 6" x 6" poles (pressure
treated on bottom portion) are set in earth, then framing, insulation,
and sheathing is installed on outside. Floor to be concrete with
drain. Each end will have a 'scissor' door for entrance and exit.
The 3000 square feet building is costing about $45,000. His car
garage and Timberframe home will set to front of hanger, facing
runway, with lots of windows facing mountains. Photo taken on frosty
morning, 12-02-04. |
|
| You can see southern scissor door going up and roller preparing
ground for more gravel. |
|
| Progress on Bill Morgan's lot as of January 24, 2007 |
 |
Photo # 1
Bill Morgan's Hanger the afternoon of January 27, 2007 |
 |
Photo # 3
Bill Morgan's Hanger as of January 30, 2007 9:00 am. |
|
|
 |